Dear All,
Is there any standard way or enhancement available to control authorization for users with certain status for WBS Element i.e. for example
Pre-requisite:
There is only 2 level of project i.e.
Lev_ WBSE_______Description
1___ 7-14.E_______summay outage controller
2___ 7-14.E.2310__ Plant/unit # 2310
2___ 7-14.E.2310__ Plant/unit # 2220
Project Controller (authorization role assigned "Z_PS_OP7_OTGCON_C") have all project level authorization
Plant/Unit Controller (authorization role assigned "Z_PS_OP7_PLNTOTG_C_2310") have only level 2 authorization with enhancement that we did in system by Z table.
User ID_ Plant #
123345_ 2310
122455_ 2220
Issue:
After System Status released and User Status approved the WBS basic date for Plant/Units should be restricted from updating/changing by Plant/Unit Controller level and only project controller should have this authority.
Solution required:
Can any one tell how to control this scenario either by standard or enhancement available to control authorization
BR
Saqib Usman