How to Control authorization for users with certain status for level 2 WBS Element

$
0
0

Dear All,

 

Is there any standard way or enhancement available to control authorization for users with certain status for WBS Element i.e. for example

 

Pre-requisite:

 

There is only 2 level of project i.e.

 

Lev_ WBSE_______Description

1___ 7-14.E_______summay outage controller

2___ 7-14.E.2310__ Plant/unit # 2310

 

2___ 7-14.E.2310__ Plant/unit # 2220

 

 

Project Controller  (authorization role assigned "Z_PS_OP7_OTGCON_C") have all project level authorization

 

Plant/Unit Controller (authorization role assigned "Z_PS_OP7_PLNTOTG_C_2310") have only level 2 authorization with enhancement that we did in system by Z table.

 

User ID_ Plant #

123345_ 2310

122455_ 2220

 

 

Issue:

 

After System Status released and User Status approved the WBS basic date for Plant/Units should be restricted from updating/changing by Plant/Unit Controller level and only project controller should have this authority.

 

Solution required: 

 

Can any one tell how to control this scenario either by standard or enhancement available to control authorization

 

BR

Saqib Usman   