Hello,
I want to create a manual material reservation against a WBS element in reference to a BOM which uses a special procurement key at component level. This special procurement 70 uses the following configuration points:
- Procurement type: External procurement
- Withdrawn alternate plant indicator: checked
- Issuing plant: 0410
When creating the reservation with MB21, the BOM referenced is created in plant 0100. I was expecting component reservations created from plant 0410 but not. All reservations created are from plant 0100. Any ideas why the special procurement key is NOT taken into account in this scenario using MB21?
On the other hand, I successfully tested this procurement key within a PM order; all component reservations created are from plant 0410, as expected.
Thanks for your help.
Christian