Hi Experts,
We are implementing classic scenario in SRM 7.13 system and due to some unknown issue PO is not getting created in ECC. PO no.gets updated in BBP_PD and status of SC change to 'Item in Transfer Process'.However PR is getting created without any issue.
We have maintained below settings in SRM system:
1) Attribute BSA is set to ZEC - Document type created for PO and PR in ECC. When we go for the search help in ppoma_bbp option we get ZEC for PR only.
2) Number Range in SRM :
Same no. range is defined in ECC with external checked for PO.
3) All other settings are maintained correctly.
There is no error message generated in rz20.But after executing 'BBP_SC_AUTO_RETRANSFER' status change to Error in transmission and Rz20 message is Error in creating follow on documents.
Please provide information to resolve the issue.
Thanks,
Ankur Goyal